Eldorado Gold Corporation, ("Eldorado" or "the Company") today announces the Company's 2017 operating results and preliminary cash costs, and provides partial production and cash cost guidance for 2018.
- Gold production of 285,919 ounces (including pre commercial production from Olympias); vs revised guidance of 280,000-310,000 ounces (including a Q4 revision at Kisladag). In addition, the Company produced 7,061 ounces of gold in the fourth quarter from a bulk sample at its newly acquired Lamaque project in
Quebec . - Cash operating costs averaged
$509 per ounce, in-line with revised third quarter guidance of$500 per ounce. - All in sustaining costs expected to be approximately
$900 per ounce, in-line with revised third quarter guidance of$900 per ounce. - Closed the year with total liquidity of approximately
$730 million , including$480 million in cash, cash equivalents and term deposits, and$250 million in undrawn lines of credit. - Completed acquisition of
Integra Gold Corp. ("Integra"), commenced pre-feasibility work (including test mining), and advanced construction of the Lamaque mine and refurbishment of the associated Sigma mill. - Olympias Phase II completed commissioning and achieved commercial production on
December 31 . - Announced in November intention to move the Skouries project into care and maintenance due to continued permitting delays. Skouries is expected to bgrae fully ramped down in Q1 2018.
Hellas Gold S.A. ,Eldorado's Greek subsidiary, entered into arbitration proceedings with the Greek Government and the proceedings are expected to conclude onApril 6, 2018 .- Continued exploration success at Lamaque (
Canada ), Bolcana (Romania ), Efemcukuru (Turkey ), and Stratoni (Greece ). - Continued improvement to the overall safety record with a reduction in the total recordable injury frequency rate for the third consecutive year.
George Burns appointed President and CEO in April.- Reconfigured the Board of Directors with retirements of
Paul Wright andJonathan Rubenstein and the appointment of Dr.George Albino as the new Chair.
"2017 was a year that was overshadowed by political headwinds in Greece and technical challenges at Kisladag," said George Burns , President and Chief Executive Officer. "With that said, I am very proud of how our team handled the opportunities and challenges of 2017. We completed the Integra acquisition, succeeded in declaring commercial production at Olympias Phase II at year-end and commenced the immense amount of technical work at our key Kisladag, Skouries and Lamaque assets. "
"2018 is already proving to be a busy year, full of catalysts, with development underway at Lamaque and new or updated technical studies for Lamaque, Skouries and Kisladag. All three studies are expected to be completed by the end of the first quarter, which will then drive the plan for the remainder of the year. Our overarching goal for 2018 and beyond is to move Eldorado back into a growth phase and create value for all our stakeholders."
2018 Partial Operating and Financial Guidance
The Company is providing partial operating and financial guidance for 2018 at this time as the technical teams continue to work on the required metallurgical testwork on the Kisladag orebody. The Company expects to be able to deliver guidance for the full year at the end of the first quarter when a sufficient amount of metallurgical testwork is completed and the technical study is complete.
Full year gold production of 160,000-190,000 ounces is expected from Olympias Phase II, Efemcukuru, and pre-commercial production at Lamaque, in addition to base metal sales and by-product credits from Stratoni and Olympias Phase II production respectively.
The Company has approximately $480 million in cash, cash equivalents and term deposits and $250 million in undrawn credit lines. The Company continues to review all general and administrative, capital and discretionary spending. Excluding Kisladag Q1 sustaining capital of $11 million , sustaining capital for mining operations in 2018 is estimated to be approximately $43 million , or $35 million for gold mining operations. Also excluding Kisladag, planned expenditures for mining development are expected to total $191 million , with the bulk of this anticipated to be spent in the development of the recently acquired Lamaque development project in Quebec . Exploration expenditures in 2018 are budgeted at $25 million (40% expensed and 60% capitalized), with a balanced focus on resource delineation and brownfield drilling at existing operations, and project generation within our regions of operation.
General and administrative expense for the year is expected to be approximately $45 million .
TURKEY
Kisladag
In 2017 the revised production guidance for Kisladag was between 170,000-180,000 ounces of gold at cash costs of $500-550 per ounce. Total production of 171,358 ounces was due to lower than expected recovery rates and slower leaching from sections of the leach pad. While gold production improved in the final quarter to just over 44,000 ounces, inventory levels over the year increased by approximately 50,000 ounces. The average ore grade placed on the leach pad during the year was 1.03 grams per tonne gold and the average cash operating cost was $500 per ounce.
In the first quarter of 2018, Kisladag is expected to place 3.1 million tonnes of ore on the leach pad at a grade of 1.25 grams per tonne gold, producing 40,000-50,000 ounces of gold at cash operating costs of $550-650 per ounce. Sustaining capital expenditure for the first quarter is expected to be $11 million . The Company is continuing to evaluate all options at Kisladag and expects to release the results of the technical study by the end of the first quarter. At that time, guidance will be provided for the remainder of 2018 for Kisladag.
Efemcukuru
During 2017, Efemcukuru met production guidance of 95,000-105,000 ounces of gold at cash costs of $525-575 per ounce, finishing the year with just over 96,000 ounces of gold produced at cash operating costs of $524 per ounce.
In 2018, Efemcukuru is expected to mine and process over 480,000 tonnes of ore at an average grade of 7.0 grams per tonne gold, producing 90,000-100,000 ounces of gold, at operating costs of $530-570 per ounce. Sustaining capital expenditures for 2018 are forecast to be approximately $20 million , spent primarily on underground mine development, equipment purchase and rebuilds, and various small capital projects.
GREECE
On September 14, 2017 , Hellas Gold received formal notice from the Greek Ministry of Finance and Ministry of the Environment and Energy initiating Greek domestic arbitration proceedings. The arbitration notice alleged that the Technical Study for the Madem Lakkos Metallurgical Plant for treating Olympias and Skouries concentrates in the Stratoni Valley , submitted in December 2014 , is deficient and thereby is in violation of the Transfer Contract and the environmental terms of the project. The arbitration proceedings are expected to conclude on April 6, 2018 and the Company is confident that the Technical Study is robust and consistent with the Transfer Contract, the Business Plan and the approved environmental terms of the project.
Olympias
On December 31, 2017, the Company achieved commercial production at Olympias Phase II. Over the month of December the mine satisfied our internal requirements regarding throughput and achieved mining grades and metallurgical performance. We are still working to improve dilution at the mine, flotation selectivity in the processing plant, and are working on the tailings handling system.
The Company is constructing a paste plant and installing an additional tailings filter press to provide maximum flexibility on paste and tailings handling to eliminate future bottlenecks. The filter press is expected to be commissioned during the first quarter 2018 and the paste plant is expected to be commissioned during the second quarter 2018. The start of the construction of the paste plant was delayed due to the permit from the Greek Government not being issued until September 2017.
In 2018, Olympias is expected to mine and process 390,000 tonnes of ore at an average grade of 8.4 grams per tonne, producing 55,000-65,000 ounces of gold, at operating costs of $550-650 per ounce. For 2018, sustaining capital expenditure is expected to be $15 million and development capital expenditure is expected to be $30 million .
Skouries
Project development was slowed considerably in 2017 due to continued permitting delays throughout the year. The Company announced its intention to move the project into care and maintenance in November 2017 and expects to be fully ramped down in Q1 2018. Some final earthworks are currently being carried out after some storm damage occurred during Q4 which increased the work required in the tailings area.
Development capital expenditure at Skouries for 2018 is expected to be $20 million as the project fully transitions to care and maintenance. Ongoing care and maintenance costs are estimated to be $3-5 million per year once fully ramped down.
Stratoni
During 2017, Stratoni processed 153,000 tonnes of ore at grades of 6.0% lead, 9.5% zinc and 159 grams per tonne silver, compared to original guidance of 200,000 tonnes of ore at grades of 6.0% lead, 9.7% zinc and 155 grams per tonne silver. Production was lower due to slower development of the deepest drive which limited access to some ore.
For 2018, Stratoni is expected to process 160,000 tonnes of ore at grades 7.2% lead, 8.7 % zinc and 175 grams per tonne silver. Sustaining capital expenditure at Stratoni is expected to be $8 million and development capital expenditure is expected to be $4 million for the year.
CANADA
Lamaque
During 2017 the Company completed the Integra acquisition and began work at its 100% wholly-owned Lamaque project. In addition to the ongoing resource upgrade and resource expansion drilling, the Lamaque pre-feasibility study continued on schedule and is expected to be complete with maiden reserves by the end of the first quarter 2018.
During 2017 test mining extracted 47,750 tonnes of ore with an average head grade of 8.6 g/t gold, with approximately 35,400 tonnes processed at a nearby custom milling facility. Results from the first two batches (32,000 tonnes) indicate that gold grade was in line with expectations and recoveries were slightly higher than anticipated at an average 95.4% for the toll treatment.
Capital expenditures at Lamaque in 2018 are forecast to be $120 million , including $20 million of capitalized mine operating costs. The Company expects to extract roughly 200,000 tonnes of ore grading 7.29 grams per tonne gold, containing approximately 40,000 ounces and anticipates toll milling a portion of the ore and producing 15,000 to 25,000 ounces.
Commercial production remains forecast for 2019 and is expected to be confirmed with the release of the pre-feasibility study.
ROMANIA
Certej
The Company expects to spend approximately $9 million in development capital during 2018 with the focus on continuing infrastructure projects and advancing permitting and support engineering, as defined in the 2015 Feasibility Study.
BRAZIL
Tocantinzinho
A construction decision at Tocantinzinho has been deferred until all permits are in place and a development project review completed. Development capital spending in 2018 is expected to be $8 million .
2017 Exploration Review
Highlights of the Company's exploration program in 2017 included:
- Lamaque resource upgrade and resource expansion drilling: Over 31,000 metres of drilling at the Triangle deposit were completed since the July acquisition of Integra. Drilling has confirmed the quality of the current resource and highlights the upside potential of the Lamaque project, including high-grade intercepts from new zones at Triangle.
- Completion of the year-one drilling program at Bolcana,
Romania : Results of over 23,000 metres at our new Bolcana porphyry project confirm the size and potential of the system. - Resource conversion drilling at Efemcukuru: Infill drilling of inferred resources in the Kestane Beleni vein continued to intersect ore grades and widths, while exploration drilling at the nearby Kokarpinar vein has identified a new high-grade shoot.
- Exploration development and underground resource expansion drilling at the
Stratoni Mine : Development of the hangingwall exploration drift continued through the year, allowing completion of over 5,900 metres of underground exploration drilling that demonstrated continuity of the Mavres Petres orebody into previously untested areas.
Corporate
Board and Senior Management Changes
During 2017, the following changes were made to the Board of Directors and to Senior Management:
- Dr.
George Albino appointed as Chair, effectiveJanuary 1, 2018 George Burns appointed as President and CEO, and elected to the Board of DirectorsPaul Wright andJonathan Rubenstein resigned as directors- Reduction in the Board size to eight directors (from 10) as well as reduced individual director and overall Board compensation
Jason Cho promoted to Executive Vice President, Strategy and Corporate Development
Subsequent to year-end, and following the Company's announcement of December 27, 2017 , further Committee changes include:
Compensation Committee
Steve Reid appointed as Chair to replaceJonathan Rubenstein - Dr.
George Albino to replaceRobert Gilmore
Sustainability Committee
Michael Price appointed as Chair to replaceSteve Reid Robert Gilmore to replace Dr.George Albino
No changes were made to the composition of the Audit Committee or the Corporate Governance and Nominating Committee.
Dividend
Pending the results of the technical reports and potential subsequent capital requirements, the Company is suspending cash payment of its semi-annual dividend payment effective the first quarter of 2018.
2017 Fourth Quarter and Year End Financials Announcement
The 2017 Fourth Quarter and Year End Financial Statements will be released after the market closes on March 21 , 2018.


